The Numbers Behind America’s Underground Utility Strike Problem
Hundreds of underground utility strikes happen every day in the US, and the latest data shows the problem isn’t going away despite decades of damage-prevention efforts.

Key Takeaways
- 213,985 unique utility damage reports were recorded in 2025, equivalent to roughly one reported incident every 2.5 minutes.
- The CGA Damage Index reached 102 in 2025, the second year in a row that it increased and its highest level under the current methodology, above its 2022 baseline of 100.
- Utility damage costs far more than direct repairs. CGA estimates the total annual economic impact at $83.2 billion, with direct repairs accounting for only $4.9 billion (5.9%).
- Excavation safety increasingly requires another layer of protection based on real-time utility detection and visibility into what is actually underground while excavation is taking place.
It is easy to think of underground utility strikes as separate, isolated incidents. One crew, one damaged line, one bad day on the jobsite. But national utility strike statistics tell a very different story.
The scale of the problem across the United States points to systemic excavation safety issues in how the industry avoids buried infrastructure. Understanding the numbers behind underground utility strikes highlights how serious the problem is and how current detection methods, which focus on pre-excavation records and data, are falling short.
How Common Is Underground Utility Damage?
The simple answer is that utility strikes are very common across the United States.
The best data on strikes in the US comes from the Common Ground Alliance (CGA), a nonprofit organization that promotes utility damage prevention across North America. Every year, the CGA publishes the DIRT Report, which includes data from the Damage Information Reporting Tool (DIRT), an online portal where users can report utility damage incidents and near misses during excavation.
The 2025 DIRT Report shows 213,985 unique damage incidents in the US during the year. That translates to:
- Almost 18,000 damages a month
- Around 586 incidents a day
- A strike roughly every 2.5 minutes.
It is important to remember that these are self-reported numbers. Therefore, the true figure is likely significantly higher, with many utility strikes going unreported.
In fact, the CGA released an Economic Impact Study in August 2026 with a much higher estimate of 668,999 damage incidents during 2025. This figure is based on quantitative modeling using DIRT data, national damage volumes, government data, and feedback from CGA members and industry executives. Almost 3 times higher than the self-reported figure, the modeled estimate translates to over 1,800 damage incidents a day and over a strike a minute.
The problem is visible at the state level, too. In Texas, a KERA News analysis of Railroad Commission data found that excavators damaged gas and liquid pipelines more than 4,800 times from the beginning of 2026 through May 31st. KERA also found that in almost a third of cases, the excavators had not contacted the state’s 811 Before You Dig notification center.
Regardless of which figure you use, the answer to how common is underground utility damage? Is worryingly too high. But even more worrying is that the numbers are trending in the wrong direction.
The CGA Damage Index is a metric developed to track changes in buried utility damage relative to excavation and 811 notification activity, rather than simply counting raw damage reports. The CGA introduced the metric in 2022 with a baseline score of 100. In 2025, the CGA Damage Index surpassed this value, reaching 102. This was the second year in a row that it increased. The latest result indicates that damage is increasing relative to the underlying level of digging activity, not merely rising due to more construction activity.
What a “Utility Strike” Actually Costs
These numbers show that an underground utility strike is not an unusual event reserved for major infrastructure projects or extreme excavation conditions. It is a recurring consequence of the current construction and excavation practices. However, counting damaged utilities only tells part of the story.
A broken gas main, fiber line, water pipe, or electrical cable creates costs that continue long after the excavator stops digging. The immediate repair is often the most visible expense, but it can represent only a small portion of the total impact.
CGA’s 2026 Economic Impact Study estimates that underground utility damage creates $83.2 billion in annual economic impact in the United States. That works out to more than $227 million every day. Of that total, only $4.9 billion, or 5.9%, comes from direct utility repair.
Put another way, CGA’s analysis indicates that for every dollar spent repairing the damaged utility itself, there are nearly $16 in additional downstream impacts. Those costs include:
- Business and Economic Disruption: Lost revenue, outages, delayed projects, and reduced productivity.
- Community and Environmental Impacts: Road and property restoration, public-facility disruption, and environmental remediation.
- Operational Response: Emergency services, traffic control, investigations, insurance, and regulatory activity.
- Human Impacts: Injuries, fatalities, medical costs, lost wages, and other consequences.
One of the most important findings is that the highest costs do not come from major incidents that make national headlines. CGA estimates that moderate incidents account for approximately $64.5 billion, more than three-quarters of the total economic impact.
That changes how contractors and excavation leaders should think about utility damage prevention. A strike does not need to produce an explosion, evacuation, or prolonged outage to become expensive. A damaged fiber line that disrupts communications, a water main that closes a road, or a gas service line that interrupts nearby businesses can create substantial costs even when nobody is injured.
The Strikes That Happen Every Week
Statistics can feel abstract at times, and it is easy to get lost in the numbers and forget the real-world situations we are actually talking about. Consider the following incidents reported across the United States in the weeks leading up to fall 2026.
- In Wilmington, North Carolina, on August 28, a construction crew struck a natural gas line, prompting an emergency response and temporarily affecting nearby businesses. Local reporting noted that it was the area’s second gas leak in less than a month.
- A similar pattern appears in North Portland, Oregon, a construction crew struck a natural gas supply line on August 31, triggering a response from Portland firefighters and NW Natural crews. No injuries were reported, but the incident required an emergency response to contain the leak and protect people nearby.
- On September 11, in Eastaboga, Alabama, a third-party excavator struck and ruptured a Southern Natural Gas transmission pipeline. The affected segment was shut down and the area secured. No injuries or fire were reported, but the incident demonstrates that even major transmission infrastructure remains exposed to third-party excavation activity.
- Just three days later, in Kansas City, Kansas, on September 14, heavy equipment struck a natural gas line in the Armourdale neighborhood. The rupture prompted evacuations of homes and businesses along part of Kansas Avenue while emergency responders and utility crews secured the area. The utility company responsible for the strike had already been fined $27,500 for 25 violations of local prevention laws in 2025, and regulators issued 65 notices of noncompliance that year.
These are not isolated examples from different eras. They occurred within weeks, across different states, and involved different parts of the natural gas network. Underground utility strikes happen frequently enough that every excavation crew should treat them as a routine operational risk rather than a remote possibility.
That distinction is important for excavation safety. The objective should not be to react effectively after a strike. It should be to prevent the excavator from making contact with the utility in the first place.
Why the Number Keeps Climbing Despite 811, Locating, and Mapping
Before excavation begins, contractors are expected to follow the applicable 811 Before You Dig process, wait for locators to identify underground facilities, review the markings and records, and use safe excavation practices around marked utilities.
While these steps remain critical, they are pre-dig controls. Once the excavator starts moving soil, physical conditions can differ from what the crew expected.
- Paint markings can fade or disappear.
- Records can be incomplete or inaccurate.
- A utility line may be deeper or shallower than expected.
- Older infrastructure may not appear in modern records.
- Some facilities are difficult to locate using conventional methods.
Urban underground infrastructure is also increasingly dense. Multiple utilities can share the same corridor, while newer communications, water, electrical, and other infrastructure is installed around older facilities.
The number keeps climbing because the task is getting harder: projects add more buried infrastructure to an already vast, complex network, and the accuracy of pre-dig utility-damage prevention techniques isn’t improving. The industry needs to rethink utility detection, making it an active part of the excavation process rather than restricting it to a pre-dig checklist.
Real-Time Utility Detection: What Will Move The Numbers Down
Even with reliable 811 services, accurate records, timely locating, clear markings, potholing, and safe excavation practices, a fundamental gap remains between knowing where a utility is expected to be and seeing what is actually underground while digging.
That is where real-time utility detection can add a new layer of protection.
Ground Penetrating Radar (GPR) integrated directly into excavation equipment can provide information at the point where the risk actually occurs: the digging bucket. Instead of relying exclusively on marks made before excavation begins, the operator can receive live information about subsurface conditions as the machine advances. This changes the role of detection technology from a one-time survey to an active part of the excavation process.
RodRadar’s Live Dig Radar® (LDR), for example, integrates GPR into the excavator bucket to provide real-time utility detection during digging. The system alerts operators to buried utilities before the bucket reaches them, adding a final line of defense against utility damage.
It does not make 811, utility locating, or potholing unnecessary. It complements those practices by addressing a different point in the excavation workflow. The principle is straightforward: if the highest risk occurs when the bucket enters the ground, then damage prevention should not end when the locate markings are completed. Live information at the point of excavation can help crews identify unexpected subsurface conditions before they become an underground utility strike.
The Bottom Line
So, how common is underground utility damage? Far too common given how preventable most utility strikes are. Damage to buried infrastructure is not simply an occasional consequence of excavation. It is a persistent safety and economic failure of the construction industry.
For an industry that has spent years trying to reduce utility strikes, the next step is not simply doing more of the same before excavation begins. It is giving crews better visibility at the moment when prevention matters most. The good news is that utility damage prevention can now follow the excavator bucket into the ground, giving the operator real-time data on subsurface conditions.
By combining real-time utility detection with pre-dig locating techniques, contractors can minimize the risk of utility damage and work towards a future of zero strikes.
FAQs
How often does underground utility damage happen in the U.S.?
CGA recorded 213,985 unique damage incidents in the US during 2025, equivalent to roughly one reported incident every 2.5 minutes. However, these are self-reported incidents, and separate modeling suggests the true number could be more than 3 times higher.
What is the CGA Underground Utility Damage Index?
The CGA Damage Index is a metric that tracks changes in underground utility damage relative to excavation and 811 notification activity. Introduced in 2022, with a baseline score of 100, the index reached 102 in 2025, its highest level under the current methodology.
How much does a utility strike actually cost?
While infrastructure strike costs depend on a wide range of factors, CGA analysis estimates the average cost for different utility types to be:
- Oil: $699.7K
- Electric: $150.8K
- Sewer: $149.9K
- Natural Gas: $146.9K
- Water: $129.4K
- Telecom: $100.5K
What’s the difference between locating and real-time detection?
Utility locating identifies where known underground facilities are expected to be before excavation, while real-time detection provides information about subsurface conditions as digging occurs. The two approaches can work together to provide both pre-dig planning and live visibility during excavation.
Is underground utility damage really preventable?
Yes. Most underground utility damage is preventable, and the Common Ground Alliance says so too. Getting there takes several layers of protection working together, not one safeguard. Those layers include 811 “Call Before You Dig” locates, survey mapping to find unknown infrastructure, and potholing to confirm utility locations visually.
Each of these steps happens before digging starts, so none of them protects against a mismarked, abandoned or unmapped utility once the bucket is in the ground. That’s where most strikes happen. Real-time detection during excavation, such as LDR Excavate™, closes this gap by giving operators live visibility into what’s below the bucket as they dig. It’s the final layer that brings zero strikes within reach.
Do I still need to call 811 if I use real-time detection equipment?
Yes. Real-time utility detection should complement, not replace, the applicable 811 notification and locating process. 811 helps identify known utilities before work begins, while detection technology can provide additional information as excavation progresses. Utilizing 811 services is also a legal requirement in many states.